21 May WHICH ACT GIVES AN INTERESTED PARTY JUDICIAL CHALLENGE IN FEDERAL COURT?
In a solicitation for the production of survival rafts, the navy
provided detailed design specifications for the process by which the contractor
was to bond the rubber seams. During testing, the seams separated at lower
pressure levels than the contract specified. The navy is considering
terminating the contract for default. What is the most likely outcome if the
contractor challenges this action?
a.
The
contractor will prevail because the navy expressly warranted that the raft
would meet all performance specifications.
b.
The
navy will prevail because the contractor bears the ultimate responsibility for
any item it delivers.
c. The contractor will
prevail if it can show that it followed the navy’s manufacturing process
precisely.
d.
The
navy will prevail because the contractor was an experienced manufacturer.
5.
Which act gives an interested party judicial challenge in federal
court?
a.
Appropriations
Act
b.
Administrative
Procedure Act
c. Competition in
Contracting Act
d.
Small
Business Act
6. Which act allows
the government to recognize the assignment of contracts as security for loans
needed for defense contract performance?
a.
Assignment of Claims Act
b.
Authorization Act
c.
Appropriations Act
d.
none of the above
7.
Which of the following can be participants in a protest?
a.
defendant, plaintiff, judge
b.
contracting officer, interested party, Government Accountability
Office (GAO), federal courts
c.
contracting officer, plaintiff, GAO
d.
none of the above
8.
Which of the following represents one of the most common methods
of determining how much one should pay for an equitable adjustment?
a.
actual cost
b.
assumption
c.
comparative
d.
both B and C
9.
__________ is/are reasonable grounds for an improper
agency evaluation protest.
a.
relaxation of the announced
award criteria by the procuring agency
b.
imposition of additional
unannounced criteria
c.
both A and B
d.
none of the above
10.A solicitation defect may include
which of the following?
a.
denial of permission to the incumbent contractor to compete on the
contract
b.
ambiguity in the requirements being solicited
c.
requests for more contractor support than previously obtained
d.
none of the above
Part II: Fill-in-the-Blank(2
points each)
11.One common reason
for a protest is improper exclusion from the _________________range.
12.There are three
forums for filing a protest: _________________, _________________, and _________________.
13.If a party in a
dispute doesn’t like the decision issued from the Court of Appeals for the
Federal Circuit, their last appeal is with the _________________viawrit of certiorari.
14.List the steps involved in the assignment of
claims process.
1.
2.
3.
4.
5.
6.
7.
8.
15.A(n) _________________permits
contractors to assign claims on government contracts to financing institutions
as collateral for loans.
16.The government’s first choice in a dispute
resolution is to undergo_________________.
17._________________is
a process in which a third party, called a conciliator,
restores damaged relationships between parties by bringing them together,
clarifying perceptions, and pointing out misconceptions.
18.When filing a protest,
it is best to work with _________________before the situation escalates to involvethe
GAO or the judicial courts.
19.A _________________
is a request for relief that seeks to initiate the disputes process.
20._________________is
the act of an authorized government agent that formally determines that the
supplies or services submitted by a contractor satisfactorily discharge the
contractor’s duty of performance under the contract.
21.The _________________
requires that important contractual agreements be reduced to writing if the
parties wish to make the agreement legally enforceable.
22.That dispute/claim
decision may then be appealed to the_________________or the _________________.
23.The procedures for
filing an agency protest are as follows:
1.
2.
3.
4.
5.
24.Where a
contractor’s reasonable interpretation of contract requirements differs from
the government’s, but the contractor is ordered to perform to the higher government
standard, the contractor is entitled to its _________________.
25.One of the
drawbacks to filing a protest with the GAO is that, once a decision is made,
the GAO lacks the_________________ to enforce the decision.
26.Suspected
violations of the Procurement Integrity Act will not be heard by the GAO.
Instead, the protestor must file a protest with the federal agency responsible
for the procurement within _________________days of discovering the violation.
27.The steps for
filing a protest are as follows:
1.
2.
3.
4.
5.
28.At any time during
a protest, one or more parties may request assistance in the form of either
negotiation assistance, where the GAO attorney offers to assist the parties in
reaching an agreement on resolving the matter, or outcome prediction, where the
GAO attorney advises the parties of the attorney’s view of the likely outcome
based on the record so that the likely unsuccessful party may take appropriate
action to resolve the protest. These processes areexamples of _________________.
29.A protest filed as
a judicial challenge in federal courts must go through the Court of _________________.
30.A(n)_________________ entitles the contractor to receive certain additional
costs of performance, plus a reasonable profit on those costs.
31.A(n) _________________defect
is a defect that existed at the time of government acceptance but that could
not be detected via reasonable inspection.
Part III: True-or-False (1 point
each)
32.
No law compels compliance
with the GAO, and every so often, an agency chooses not to implement the GAO
opinion.
a.
true
b.
false
33.
A subcontractor cannotfile a claim directly with the
contracting officer.
a.
true
b.
false
34.A general change is one that is beyond the
general scope of the contract and thus cannot be ordered by the contracting
officer under the contract’s changes clause.
a.
true
b.
false
35.A contracting officer may
reconsider, withdraw, or rescind a final decision before the expiration of the
appeals period.
a.
true
b.
false
36.The course of performance
rule applies when one party is aware of how the other is interpreting a term, and
acquiesces in that interpretation. When this happens, he or she is bound by
that interpretation.
a.
true
b.
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Writedemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.
