1.0
2.0:
Product Research
· Task 1: Find similar designs
1. Members Responsible: everyone
2. Objective: To find current technology on the market
3. Deliverables: A literature survey
4. Required Resources: A computer for research
5. Schedule/Cost Estimate: February 1-February 7. No cost
· Task 2: Find potential competition
1. Members Responsible: everyone
2. Objective: To find existing products with the same application
3. Deliverables: Links to the products
4. Required Resources: A computer for research
5. Schedule/Cost Estimate: February 7-February 14. No cost
Product Planning
· Task 1: Anticipate manufacturing requirements
1. Members Responsible: Devontay, Mohanned
2. Objective: To consider future costs, personnel, and equipment needed
3. Deliverables: A few paragraphs
4. Required Resources: A computer for research
5. Schedule/Cost Estimate: February 14-February 21. No cost
· Task 2: Find customer requirements
1. Members Responsible: everyone
2. Objective: To find the needs of the customer
3. Deliverables: Survey results
4. Required Resources: survey, and potential customers
5. Schedule/Cost Estimate: February 21-February 28. No cost
Product Development
· Task 1: Design product
1. Members Responsible: Noah, Dakota
2. Objective: To brainstorm and develop ideas for the product
3. Deliverables: Sketches and a decision on how the product will work
4. Required Resources: A computer
5. Schedule/Cost Estimate: February 28-March 7. No cost
· Task 2: Create models and drawings for components
1. Members Responsible: Devontay, Mohanned
2. Objective: To create the components and drawings
3. Deliverables: Models and prints
4. Required Resources: computer with modeling capabilities
5. Schedule/Cost Estimate: March 7-March 14. No cost
Testing and Validation
· Task 1: Analyze stresses in ANSYS
1. Members Responsible: Adam, Noah
2. Objective: To anticipate potential failure in our product
3. Deliverables: Stress and deformation results
4. Required Resources: A computer with ANSYS
5. Schedule/Cost Estimate: March 14-March 21. No cost
· Task 2: Create Prototype
1. Members Responsible: Dakota
2. Objective: To create and test a prototype
3. Deliverables: prototype
4. Required Resources: 3D printer, and metal spring
5. Schedule/Cost Estimate: March 21-March 28. Cost-printing material ($2)
Product Development
· Task 1: Find a manufacturer (molds and assembly process)
1. Members Responsible: everyone
2. Objective: To find a manufacturer to create our product
3. Deliverables: a manufacturer report
4. Required Resources: A computer, and connections
5. Schedule/Cost Estimate: undetermined. Cost-?
· Task 2: Develop marketing plan and sell product
1. Members Responsible: everyone
2. Objective: To finalize the product into the market
3. Deliverables: finished product
4. Required Resources: manufacturing process and potential sellers
5. Schedule/Cost Estimate: undetermined. Cost-?
| Product Planning | |
| Design Organization: Group 5 | Date: 2/25/18 |
| Proposed Product Name: Reel Quik | |
| Task 1 | Name of Task: Anticipate Manufacturing Requirements |
| Objective : To consider future costs, personnel, and equipment needed | |
| Deliverables: A few paragraphs
|
|
| Decisions needed:
Decision 1: Determine manufacturing possibilities Decision 2: |
|
| Personnel needed
Title: Designer Hours: 3 Percent full time: Title: Hours: Percent full time: |
|
| Time estimate Total hours: 3 Lapsed time(include units): | |
| Sequence: Predecessors: Successors:
Start Date: 2/14/18 Finish Date: 2/21/18 |
|
| Costs: Capital Equipment N/A Disposables: N/A | |
| Task 2 | Name of Task: Find Customer Requirements |
| Objective : To find the needs of the customer | |
| Deliverables: Survey results
|
|
| Decisions needed:
Decision 1: Determine how to meet the customer needs Decision 2: |
|
| Personnel needed
Title: Surveyor Hours: 5 Percent full time: Title: Surveyor Hours: 5 Percent full time: |
|
| Time estimate Total hours: 10 Lapsed time(include units): | |
| Sequence: Predecessors: Find potential competition Successors: product development
Start Date: 2/21/18 Finish Date: 2/28/18 |
|
| Costs: Capital Equipment Disposables: | |
| Team member: Noah | Prepared by: Noah |
| Team member: Dakota | Checked by: Dakota |
| Team member: Adam | Approved by: Noah |
| Team member: Devontay, Mohanned | |
| The Mechanical Design Process Designed by Professor David G. Ullman
Copyright 2008, McGraw Hill Form # 10.0 |
| Product Development | |
| Design Organization: Group 5 | Date: 2/25/18 |
| Proposed Product Name: Reel Quik | |
| Task 1 | Name of Task: Design Product |
| Objective : To brainstorm and develop ideas for the product | |
| Deliverables: sketches
|
|
| Decisions needed:
Decision 1: Determine how the product will work Decision 2: |
|
| Personnel needed
Title: Designer Hours: 4 Percent full time: Title: Designer Hours: 4 Percent full time: |
|
| Time estimate Total hours: 8 Lapsed time(include units): | |
| Sequence: Predecessors: customer survey Successors: create models and drawings for components
Start Date: 2/28/18 Finish Date: 3/7/18 |
|
| Costs: Capital Equipment N/A Disposables: N/A | |
| Task 2 | Name of Task: Create models and drawings for components |
| Objective : To create the components and drawings | |
| Deliverables: Models and Prints
|
|
| Decisions needed:
Decision 1: Determine if design incorporates customer needs and will work Decision 2: |
|
| Personnel needed
Title: Designer Hours: 4 Percent full time: Title: Designer Hours: 4 Percent full time: |
|
| Time estimate Total hours: 8 Lapsed time(include units): | |
| Sequence: Predecessors: Determine how product will work Successors:
Start Date: 3/7/18 Finish Date: 3/14/18 |
|
| Costs: Capital Equipment Disposables: | |
| Team member: Noah | Prepared by: Noah |
| Team member: Dakota | Checked by: Dakota |
| Team member: Adam | Approved by: Noah |
| Team member: Devontay, Mohanned | |
| The Mechanical Design ProcessDesigned by Professor David G. Ullman
Copyright 2008, McGraw Hill Form # 10.0 |
| Testing and Validation | |
| Design Organization: Group 5 | Date: 2/25/18 |
| Proposed Product Name: Reel Quik | |
| Task 1 | Name of Task: Analyze stresses in ANSYS |
| Objective : To anticipate future failures in our prodcut | |
| Deliverables: stress and deformation results
|
|
| Decisions needed:
Decision 1: Determine what loads to apply Decision 2: |
|
| Personnel needed
Title: Designer Hours: 3 Percent full time: Title: Designer Hours: 3 Percent full time: |
|
| Time estimate Total hours: 6 Lapsed time(include units): | |
| Sequence: Predecessors: Create models and Drawings Successors: Create a prototype
Start Date: 3/14/18 Finish Date: 3/21/18 |
|
| Costs: Capital Equipment N/A Disposables: N/A | |
| Task 2 | Name of Task: Create Prototype |
| Objective : To create and test a prototype | |
| Deliverables: prototype
|
|
| Decisions needed:
Decision 1: Determine if the design works as expected Decision 2: |
|
| Personnel needed
Title: Designer Hours: 3 Percent full time: Title: Hours: Percent full time: |
|
| Time estimate Total hours: 3 Lapsed time(include units): | |
| Sequence: Predecessors: Analyze stresses in ANSYS Successors:
Start Date: 3/7/18 Finish Date: 3/14/18 |
|
| Costs: Capital Equipment 3D printer Disposables: | |
| Team member: Noah | Prepared by: Noah |
| Team member: Dakota | Checked by: Dakota |
| Team member: Adam | Approved by: Noah |
| Team member: Devontay, Mohanned | |
| The Mechanical Design Process Designed by Professor David G. Ullman
Copyright 2008, McGraw Hill Form # 10.0 |
| Product Development | |
| Design Organization: Group 5 | Date: 2/25/18 |
| Proposed Product Name: Reel Quik | |
| Task 1 | Name of Task: Find a manufacturer (mold and assembly process) |
| Objective : To find a manufacturer to create our product | |
| Deliverables: A manufacturer report
|
|
| Decisions needed:
Decision 1: Determine exactly what our process requires Decision 2: |
|
| Personnel needed
Title: Designer Hours: 40 Percent full time: Title: Designer Hours: 40 Percent full time: |
|
| Time estimate Total hours: 3 Lapsed time(include units): | |
| Sequence: Predecessors: Anticipate Manufacutring needs Successors: Determine where to sell product
Start Date: Unsure Finish Date: Unsure |
|
| Costs: Capital Equipment N/A Disposables: N/A | |
| Task 2 | Name of Task: Develop marketing plan and sell product |
| Objective : To finalize the product into the market | |
| Deliverables: finished product
|
|
| Decisions needed:
Decision 1: Determine where to sell the product Decision 2: |
|
| Personnel needed
Title: Marketing Agent Hours: 40 Percent full time: Title: Hours: Percent full time: |
|
| Time estimate Total hours: 3 Lapsed time(include units): | |
| Sequence: Predecessors: find a manufacturer Successors:
Start Date: Unsure Finish Date: Unsure |
|
| Costs: Capital Equipment Disposables: | |
| Team member: Noah | Prepared by: Noah |
| Team member: Dakota | Checked by: Dakota |
| Team member: Adam | Approved by: Noah |
| Team member: Devontay, Mohanned | |
| The Mechanical Design ProcessDesigned by Professor David G. Ullman
Copyright 2008, McGraw Hill Form # 10.0 |
4.0
a.
b.
Product Planning Task 1 = = = 3 hours
References
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Writedemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.