Chat with us, powered by LiveChat Question 11. The Eugene plant of Basic Computers Inc. (BCI) wants to develop a net require | Writedemy

Question 11. The Eugene plant of Basic Computers Inc. (BCI) wants to develop a net require

Question 11. The Eugene plant of Basic Computers Inc. (BCI) wants to develop a net require

Question

11. The Eugene plant of Basic Computers Inc. (BCI) wants to develop a net requirements schedule for one model of microcomputers. The beginning inventory is 500 units and they like to carry 50 units as safety stock. The estimated demand for the next 6 weeks is 200, 250, 300, 375, 400, and 600 units.

a. What would the net requirements be for week 3?

b. What is the beginning inventory in week 5?

12. An electronics company wants to develop an MRP schedule for one of its key components, a specialized chip. The lot size is 600, the lead time is 2 weeks, there are 900 units on hand with 300 of those as safety stock and 500 already allocated. There are gross requirements for 2000 units in week 3 and 1500 units in week 5. There are 600 units scheduled to be received in week 1.

a. What is the number of units available in week 3?

b. What is the planned order receipt for week 5?

13. A company that makes inkjet printers is trying to determine a MRP schedule for the print cartridges it needs in its newest model of printer. They have gross requirements of 1000 units in week 2 and 900 units in week 4. The minimum lot size is 500 units and the lead time is 1 week. They currently have 300 units on hand that includes a safety stock of 150 and another 100 units already allocated. They have 500 units scheduled for receipt in week 1.

a. What is the number of units available in week 1?

b. What is the planned order release in week 3?

14. A manufacturing company is trying to determine the best lot-sizing approach to take when developing an MRP schedule: lot?for?lot (LFL), fixed order quantity (FOQ) using the EOQ, or period order quantity (POQ). The ordering cost is $504 per order, the inventory carrying cost is $1 per week per unit, and the annual demand for the product is 15,000 units. They are using a work schedule for a 50-week work year. They are disregarding the effects of initial inventory and safety stock at the present time. The estimated net requirements for their product for the next six weeks are:

Week 1 2 3 4 5 6
Net Requirements 100 400 200 350 600 50

a. Using LFL, what is the size of the production lot in week 3?

b. Using LFL, what is the total cost for this method?

c. What is the EOQ needed?

d. What is the beginning inventory in week 4 using FOQ method?

e. What is the total cost for using the FOQ approach?

f. What is the POQ size for production lots?

g. What is the ending inventory for week 5 using POQ method?

h. What is the total cost for using the POQ approach?

15. A company that makes construction equipment is exploring different lot sizing approaches to its MRP schedule: lot for?lot (LFL), fixed order quantity (FOQ) using the EOQ, and period order quantity (POQ). It costs $100 to set up the production line to produce hydraulic jacks and the carrying cost per unit per week is $1. Annual demand is expected to be 1550 jacks. For planning purposes, the company uses a 50-week work year and disregards the effects of initial inventory and safety stock. The net requirements for hydraulic jacks for the next six weeks are:

Week 1 2

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order