Question 41. (7 points) An automobile detailing shop has the fol

Question 41. (7 points) An automobile detailing shop has the fol

Question

41. (7 points) An automobile detailing shop has the following jobs waiting to be processed. All jobs (cars requiring detailing) must first be cleaned, then waxed.

Job C1 C2 C3 C4 C5
Cleaning Time 9 6 5 3 8
Waxing Time 6 2 7 5 4

a. What processing sequence will minimize the makespan for these jobs?

b. What is the minimum makespan for this set of five jobs?

42. (10 points) The elements required for successful implementation of the JIT/Lean philosophy include reducing setup times, performing preventive maintenance, and achieving high quality (zero defects). Discuss the problems that might arise when a kanban system (pull system) is used for production control and each of these JIT elements is not present. (In other words, what would happen if a kanban system is being used and there are long setup times, no preventive maintenance, and poor quality?)

43. (7 points) From a process known to be in control, 6 random samples of 5 units each were taken and weighed. The mean and range for each of the 6 samples are given in the following table.

Sample Mean Range
1 7.2 0.7
2 7.6 1.0
3 7.1 1.4
4 7.8 1.1
5 7.8 0.6
6 7.5 1.2
_
a. Calculate the 3? X-chart and R-chart control limits.
_
b. Calculate the mean (X) and range (R) for the following sample, which was taken from the same process at a later time.

Item number: 1 2 3 4 5
Weight: 7.5 8.08.2 7.5 7.4

Based on this sample and the control chart limits that you calculated in part (a), is the process in control? Why or why not?

44. (7 points) A company stocks a component that costs $20 per unit. Annual usage of this item is expected to be 3120 units. The firm is open for business 52 weeks per year, so weekly demand is 60 units per week, with a standard deviation of 30 units. The firm’s cost accountants have estimated that it costs $60 every time an order is placed for more components, and that carrying the item in inventory costs about $10 per unit per year. Past experience with their supplier indicates that the time from ordering more items to receipt of the shipment of those items is 21 days (assume they are open 7 days per week).

a. What quantity should be ordered each time? (Assume that the EOQ assumptions apply.)
b. What is the minimum total annual cost (ordering + holding + purchase) for managing this inventory item?
c. If the company decided that their JIT program required frequent small orders and deliveries (assume that this would mean ordering a quantity of 17 units every other day, instead of the EOQ quantity on a less frequent basis), and the costs remain the same as described above, how much higher would the total annual cost be for this item?
d. If a 90% service level is required, what reorder point should be used?

45. (7 points) The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations.

a. Using the data, calculate the expected time and variance for each activity.

Job Number Predecessor Job(s) a m b ET variance
A — 3 5 7
B A 3 4 5
C A 4 5 12
D B 1 3 5
E B, C 3 4 11
F D,E 2 4 6

b. Sketch the network diagram for the project.

c. Indicate the critical path. (You can do this by inspecting the paths – you do not have to calculate ES, EF, LS, LF). What is the expected completion time for the project?

d. What is the probability that the project will take more than 22 days to complete?

46. (2 points) Of the topics that we covered in this course, which one or ones were the most interesting and/or useful to you? Why?

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order