What is a milestone?
A. A significant event in the project

B. A mark on a chart that depicts project progress

C. An activity on the critical path

D. An activity with an uncertain completion time
Reset Selection

Mark for Review What’s This?
Question 2 of 20 5.0 Points

What is project slack?
A. The amount of time a non-critical task can be delayed without making the project late

B. The amount of time the critical path of a project can be delayed without making the project late

C. The amount of time an activity on the critical path can be delayed without making the project late

D. The difference between how long the project would take if all tasks were completed based on their pessimistic versus optimistic time estimates
Reset Selection

Mark for Review What’s This?
Question 3 of 20 5.0 Points

For which purpose is simulation NOT used with regard to project scheduling?
A. To overcome the limitations associated with statistical techniques used to develop probability of completion time estimates

B. To investigate the range of project completion times

C. To investigate the distribution of project completion times

D. To verify the accuracy of the optimistic, pessimistic, and most likely time estimates

Question 4 of 20 5.0 Points

Technical dependencies on a project plan are easiest to see on a:
A. Gantt chart.

B. GERT chart.

C. PERT/CPM chart.

D. Work Breakdown Structure.

Question 5 of 20 5.0 Points

PERT was originally used for what type of project?
A. Construction

B. R & D

C. Military

D. Computer software development

Question 6 of 20 5.0 Points

Which of the following is NOT an element of the Gantt chart?
A. Actual progress

B. Variance of the critical path

C. The current date

D. Scheduled milestones

Question 7 of 20 5.0 Points

Which of the following is typically used as the best estimate of task duration?
A. Expected time

B. Pessimistic time

C. Optimistic time

D. Most likely time

Question 8 of 20 5.0 Points

Which of the following terms is most closely associated with a task required by the project?
A. Activity

B. Event

C. Milestone

D. Network

Question 9 of 20 5.0 Points

What is the expected time to complete a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days, respectively?
A. 3

B. 4

C. 4.3

D. 4.7

Question 10 of 20 5.0 Points

What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days, respectively, assuming the estimates were made at the 99% plus level?
A. .444

B. .667

C. 1.212

D. 1.469

Question 11 of 20 5.0 Points

The amount of time a noncritical task can be delayed without delaying the project is called:
A. surplus.

B. flop.

C. slack.

D. critical time.

Question 12 of 20 5.0 Points

Slack is calculated as:
A. LFT – EST.

B. LFT – LST.

C. LST – LFT.

D. LFT – EFT.

Question 13 of 20 5.0 Points

Which of the following linkages is used to start two or more activities at the same time?
A. Finish-to-start

B. Start-to-start

C. Finish-to-finish

D. Start-to-finish

Question 14 of 20 5.0 Points

One shortcoming of the __________ network method is that it does not allow for leads and lags between two activities without greatly increasing the number of subactivities to account for this.
A. Gantt Chart

B. AON

C. MSP

D. PERT/CPM

Question 15 of 20 5.0 Points

An identifiable state resulting from the completion of one or more activities is called:
A. an event.

B. an activity.

C. a milestone.

D. a path.
Reset Selection

Question 16 of 20 5.0 Points

The major advantage of the Gantt chart is that it:
A. addresses all activities.

B. is easy to read.

C. highlights critical task of the project.

D. manages project scheduling.
Reset Selection

Question 17 of 20 5.0 Points

A(n) __________ is an identifiable state resulting from the completion of one or more activities.
A. path

B. milestone

C. critical path

D. event
Reset Selection

Question 18 of 20 5.0 Points
For any task on a critical path, its __________ must be the same as its __________.

A. LST; LFT

B. LFT; EFT

C. LST; EST

D. EST; EFT
Reset Selection

Mark for Review What’s This?

Question 19 of 20 5.0 Points
The amount of time a noncritical task can be delayed without delaying the project is called:

A. margin.

B. completion variance.

C. float.

D. variable duration.
Reset Selection

Mark for Review What’s This?

Question 20 of 20 5.0 Points
The square root of the variance of statistical distribution equals the __________ of that distribution.

A. standard deviation

B. normal probability

C. variance of the path

D. cumulative probability
Reset Selection

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order