02 May read and my price will not change
S/N | ACTIVITY | COST | |
1 | Hiring of machines | 70000 | |
2 | Direct labor for the project | 115000 | |
3 | Direct materials | 240000 | |
4 | Plan and design of the house | 35000 | |
5 | Environmental certification permit | 30000 | |
6 | Electrical work | 25000 | |
7 | Plumbing work | 25000 | |
8 | Constuction of store room and settting up | 20000 | |
9 | Site security | 15000 | |
10 | transport and storage | 25000 | |
11 | House decoration | 130000 | |
12 | Interior design | 15000 | |
13 | Painting | 35000 | |
14 | Land scaping | 30000 | |
15 | Waterproof laying and roofing | 45000 | |
16 | purcahse of windows and doors | 15000 | |
17 | bathroom fittings, and | 20000 | |
18 | Heating, ventilation and Air conditioning system | 45000 | |
19 | floor tiling | 45000 | |
20 | security system installation | 25000 | |
CONSTRUCTION COST | 1005000 | ||
21 | CONTIGENCY | 24000 | |
TOTAL COST | 1029000 |
PROJECT SCHEDULE | |||||||||
CONSTRUCTION OF A HOUSE IN ASHBURN, VIRGINIA | |||||||||
ESTIMATED COST | $1.2 MILLION | ||||||||
COST | ACTIVITY TO BE CARRIED OUT | COMMENCEMENT | PLANNED DURATION | ACTUAL START OF ACTIVITY | END | ||||
$60, 000 | Activity No 1 | Finalising on the design of the house | 58 days | 01/10/2019 | 07/09/2019 | 51 days | |||
$150 | Activity No 2 | Issuance of permit to build the house | 1 day | 05/16/2019 | 05/17/2019 | 1 day | |||
$132, 000 | Activity No 3 | Pre- Construction of the building | 100 days | 02/04/2019 | 05/05/2019 | 90 days | |||
$210, 000 | Activity No 4 | setting up the construction crane on site | 125 days | 08/03/2019 | 12/04/2019 | 125 days | |||
$190, 000 | activity No 5 | Setting up water lines underground | 80 days | 05/03/2019 | 08/25/2019 | 80 days | |||
$90,000 | Activity No 6 | Pouring the building’s concrete footings | 30 days | 09/16/2019 | 10/17/2019 | 30 days | |||
$40, 000 | Activity No 7 | Construction of foundation walls | 20 days | 09/21/2019 | 10/13/2019 | 20 days | |||
$30,000 | Activity No 8 | forming and pouring the slab | 15 days | 11/16/2019 | 12/02/2019 | 15 days | |||
$70,000 | Activity No 9 | Back fill and Compact wall | 17 days | 11/19/2019 | 12/07/2019 | 17 days | |||
$440, 000 | Activity No 10 | coming up with the structure of the building | 120 days | 12/11/2019 | 03/21/2020 | 120 days | |||
$2, 000 | Activity No 11 | Decking the floor | 30 days | 02/21/2020 | 04/02/2020 | 30 days | |||
$3, 200 | Activity No 12 | Construction of the 1st floor | 24 days | 04/11/2020 | 05/06/2020 | 24 days | |||
$9, 000 | Activity No 13 | Erecting the staircase | 14 days | 04/16/2020 | 04/30/2020 | 14 days | |||
$7, 000 | Activity No 14 | Concreting the slab of the basement | 15 days | 05/01/2020 | 05/15/2020 | 15 days | |||
$160, 000 | Activity No 15 | Concreting the second floor | 19 days | 04/21/2020 | 05/09/2020 | 19 days | |||
$150,000 | Activity No 16 | Installing an electrical system | 5 days | 04/20/2020 | 04/25/2020 | 5 days | |||
$3, 000 | Activity No 17 | Installing the building’s roofing | 10 days | 05/13/2020 | 05/23/2020 | 10 days | |||
$7, 500 | Activity No 18 | Doors and windows | 2 days | 05/30/2020 | 06/02/2020 | 2 days | |||
$2, 000 | Activity No 19 | Exterior finishes | 21 days | 06/04/2020 | 06/25/2020 | 21 days | |||
$58, 070 | Activity No 20 | Contigencies | 14 days | 06/25/2020 | 07/07/2020 | 14 day |
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Writedemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.