11. Briefly describe MRP II and closed-loop MRP.
14. If seasonal variations are present, is their incorporation into MRP fairly simple or fairly difficult? Explain briefly.
15. How does the purpose of ERP differ from the purpose of MRP II?
16. What are some unforeseen costs of ERP?
Chapter 15: Discussion and Review Questions: 5, 9, & 11 (p. 695)
5. What is the bullwhip effect, and why does it occur? How can it be overcome?
9. What impact has e-business had on supply chain management?
11. What are some of the trade-offs that might be factors in designing a supply chain?
**********************************************************************
DeVry Chicago BSOP 334 Week 5 Lab
5) End item P is composed of three subassemblies: K, L, and W. K is assembled using 3 Gs and 4 Hs; L is made of 2 Ms and 2 Ns; and W is made of 3 Zs.
On-hand inventories are 20 Ls, 40 Gs, and 200 Hs.
Scheduled receipts are 10 Ks at the start of week 3, 30 Ks at the start of week 6, and 200 Ws at the start of week 3.
One hundred Ps will be shipped at the start of week 6, and another 100 at the start of week 7. Lead times are two weeks for subassemblies and one week for components G, H, and M. Final assembly of P requires one week. Include an extra 10 percent scrap allowance in each planned order of G. The minimum order size for H is 200 units. Develop each of the following:
a. A product structure tree.
b. An assembly time chart.
c. A master schedule for P.
d. A material requirements plan for K, G, and H using lot-for-lot ordering.
6) A table is assembled using three components, as shown in the accompanying product structure tree. The company that makes the table wants to ship 100 units at the beginning of day 4, 150 units at the beginning of day 5, and 200 units at the beginning of day 7.
Receipts of 100 wood sections are scheduled at the beginning of day 2. There are 120 legs on hand. An additional 10 percent of the order size on legs is added for safety stock. There are 60 braces on hand with no safety stock requirement for braces. Lead times (in days) for all items are shown in the following table. Prepare a material requirements plan using lot-for-lot ordering.
7) Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8. Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units.
5) End item P is composed of three subassemblies: K, L, and W. K is assembled using 3 Gs and 4 Hs; L is made of 2 Ms and 2 Ns; and W is made of 3 Zs.
On-hand inventories are 20 Ls, 40 Gs, and 200 Hs.
Scheduled receipts are 10 Ks at the start of week 3, 30 Ks at the start of week 6, and 200 Ws at the start of week 3.
One hundred Ps will be shipped at the start of week 6, and another 100 at the start of week 7. Lead times are two weeks for subassemblies and one week for components G, H, and M. Final assembly of P requires one week. Include an extra 10 percent scrap allowance in each planned order of G. The minimum order size for H is 200 units. Develop each of the following:
a. A product structure tree.
b. An assembly time chart.
c. A master schedule for P.
d. A material requirements plan for K, G, and H using lot-for-lot ordering.
6) A table is assembled using three components, as shown in the accompanying product structure tree. The company that makes the table wants to ship 100 units at the beginning of day 4, 150 units at the beginning of day 5, and 200 units at the beginning of day 7.
Receipts of 100 wood sections are scheduled at the beginning of day 2. There are 120 legs on hand. An additional 10 percent of the order size on legs is added for safety stock. There are 60 braces on hand with no safety stock requirement for braces. Lead times (in days) for all items are shown in the following table. Prepare a material requirements plan using lot-for-lot ordering.
7) Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8. Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units.
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Writedemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.