Question
Question 1. 1. The production manager for the Coory soft drink company is considering the production of two kinds of soft drinks: regular (R) and diet (D). Two of her limited resources are production time (8 hours = 480 minutes per day) and syrup (1 of the ingredients), limited to 675 gallons per day. To produce a regular case requires 2 minutes and 5 gallons of syrup, while a diet case needs 4 minutes and 3 gallons of syrup. Profits for regular soft drink are $3.00 per case and profits for diet soft drink are $2.00 per case. What is the objective function? (Points : 5)
MAX $2R + $4D
MAX $3R + $2D
MAX $3D + $2R
MAX $4D + $2R
Question 2. 2. Project management differs from management of more traditional day-to-day activities because: (Points : 5)
it has limited time frame.
it has an unlimited budget.
it is more expensive.
it involves more of the workforce.
Question 3. 3. The maximum number of constraints that could define the feasible solution space is _____: (Points : 5)
2
3
4
Unlimited
Question 4. 4. A plant manager is attempting to determine the production schedule of various products to maximize profit. Assume that a machine hour constraint is binding. If the original amount of machine hours available is 200 minutes., and the range of feasibility is from 130 minutes to 300 minutes, providing two additional machine hours will result in: (Points : 5)
the same product mix, different total profit.
a different product mix, same total profit as before.
the same product mix, same total profit.
a different product mix, different total profit.
Question 5. 5. The $75 per credit hour course fee tacked on to all the MBA classes has generated a windfall of $56,250 in its first semester. “Now we just need to make sure we spend it all,” the Assistant Dean cackled. She charged the Graduate Curriculum Committee with generating a shopping list before their next meeting. Four months later, the chairman of the committee distributed the following. As the professor for the quantitative modeling course, he tended to think in terms of decision variables, so he added the left-most column for ease of use.
| Decision Variable |
Item | Cost | Note |
| A | iPads for everybody | $750/unit | Must get a cover if these are purchased |
| B | iPad covers with MBA logo | $25/unit | Not needed unless we buy iPads |
| C | Speaker series | $15,000 | Can’t afford both this and the iPads |
| D | Subscriptions to the Wall Street Journal | $10/unit | Don’t need if we have the electronic version |
| E | Subscriptions to the electronic version of the Wall Street Journal | $5/unit | Worthless without the iPads |
Which of the constraints best describes the relationship between the iPads for everyone and the speaker series? (Points: 5)
A – C = 1
A + C = 1
A – C = 0
A + C = 2
Question 6. 6. In a ________ integer model, all decision variables have integer solution values. (Points : 5)
Total
0-1
Mixed
all of the above
Question 7. 7. If a maximization linear programming problem consists of all less-than-or-equal-to constraints with all positive coefficients and the objective function consists of all positive objective function coefficients, then rounding down the linear programming optimal solution values of the decision variables will ________ result in a feasible solution to the integer linear programming problem. (Points : 5)
Always
Sometimes
Optimally
Never
Question 8. 8. When systematically formulating a linear program, the first step is to: (Points : 5)
construct the objective function
formulate the constraints
identify the decision variables.
identify the parameter values.
Question 9. 9. The critical path is the ________ path through the network. (Points : 5)
Longest
Shortest
Straightest
most expensive
Question 10. 10. In a 0-1 integer programming model, if the constraint x1 – x2 = 0, it means when project 2 is selected, project 1 ________ be selected. (Points : 5)
must always
can sometimes
can never
is already
Question 11. 11. Multiple optimum solutions can occur when the objective function is _______ a constraint line. (Points : 5)
unequal to
equal to
linear to
parallel to
Question 12. 12. A shadow price reflects which of the following in a maximization problem? (Points : 5)
The marginal gain in the objective that would be realized by adding one unit of a resource
The marginal gain in the objective that would be realized by subtracting one unit of a resource
The marginal cost of adding additional resources
The marginal gain of selling one more unit
Question 13. 13. In a ________ integer model, some solution values for decision variables are integers and others can be non-integer. (Points : 5)
Total
0-1
Mixed
all of the above
Question 14. 14. For most graphs, the constraint equations which intersect to form a solution point must be solved simultaneously: (Points : 5)
because the solution coordinates from the graph cannot be visually read with high precision.
in order to confirm the mathematically determined coordinates.
in order to determine all of the optimal point solution.
because the slope b and the y-intercept a are not always integers.
Question 15. 15. In order to transform a “>=” constraint into an equality (“=”) in a linear programming model: (Points : 5)
add a slack variable.
add a surplus variable.
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Writedemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.