07 Jun PROJ 586 Final Exam Set 1 NEW
1. (TCO A) In the _____ organization structure, the project manager is responsible for the project results, whereas the functional manager is responsible for providing the resources needed to achieve the results.
2. (TCO H) What is the longest phase of the project life cycle?
3. (TCO B) The lowest level item of any one branch of the WBS is called a(n) _____.
4. (TCO D) A _____ is a predefined set of actions that will be implemented if the risk event occurs.
5. (TCO F) _____ the project involves measuring actual progress and comparing it to planned progress.
6. (TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time.
7. (TCO G) Which of the following is not an advantage of using project management software?
8. (TCO A) Which of the following is not an example of a project?
9. (TCO C) Why are activities drawn in a serial relationship on a network diagram?
10. (TCO F) The project cost estimate is allocated to _____.
11. (TCO F) It is important to use the _____ as the standard against which actual cost is compared.
12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
Page 2
1. (TCO B) Describe the benefits of including the people who will be involved in performing the project when planning the project.
2. (TCO E)
Part 1: What are some common barriers to team effectiveness?
Part 2: Describe an example of a team project that would include barriers to success.
3. (TCO C) A project to remodel an office area has the following activities. (Hint: You will need to build an AIB diagram, perform a forward pass, and perform a backward pass to answer this question.)
Activity Duration Predecessors
A 2 months —
B 4 months —
C 4 months —
D 1 month A
E 5 months B
F 2 months B, C
G 1 month C
H 3 months E, F, G
I 2 months D, E
J 2 months G, H
Activity Duration Predecessors ES EF LS LF Slack
A 2 months — 0 2 7 9 7
B 4 months — 0 4 0 4 0
C 4 months — 0 4 3 7 3
D 1 month A 2 3 9 12 9
E 5 months B 4 9 4 9 0
F 2 months B, C 4 6 7 9 3
G 1 month C 4 5 8 9 4
H 3 months E, F, G 9 12 9 12 0
I 2 months D, E 9 11 12 14 3
J 2 months G, H 12 14 12 14 0
a) What are the critical path activities?
b) What is the project’s scheduled completion time?
c) What is the slack or float for Activity A? Show your calculations.
d) What is the slack or float for Activity E? Show your calculations.
e) What is the slack or float for Activity F? Show your calculations.
f) What is the slack or float for Activity G? Show your calculations.
4. (TCO A)
Part 1: Compare and contrast the responsibilities of a functional manager and a project manager in a matrix-type organization.
Part 2: A company manufactures furniture. Which organization structure is the most suitable? Why?
Part 3: An organization builds custom houses for urban-renewal areas. Which organization structure is the most suitable? Why?
5. (TCO D) A firm hosts data-mining servers and performs data mining for other companies that do not desire the costs of hardware, software, or expertise to data mine their data. The firm is planning to roll out faster data-mining software that will reduce the time to sift through customers’ data by a fraction of the present time.
Part 1: List and discuss the major risk-management functions from a project-management perspective for the data-mining software project.
Part 2: Describe a risk event, the consequences, and the risk-response plan for the data-mining software project.
6. (TCO F) Analyze and compare the costs of the two projects in terms of performance efficiency, budget, and schedule. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will receive only partial credit.)
Project A: The budgeted cost of work performed is $72,000, and the actual cost of work performed is $75,000. The budgeted cost of work scheduled is $73,000.
Project B: The budgeted cost of work performed is $48,000, and the actual cost of work performed is $100,000. The budgeted cost of work scheduled is $122,000.
7. (TCO B) An environmental consulting firm has been hired to clean up contaminated ground water beneath the site of a former chemical factory. The cleanup design process consists of evaluating several alternatives; preparing a conceptual design for the most appropriate alternative; evaluating the conceptual design by performing a small-scale pilot test on site; and, based on the results of the pilot test, preparing a final design. Installation of the cleanup system will be performed by subcontractors under the supervision of the consultant. Prior to installation, the consultant will work on setting up the subcontracts by preparing specifications, prequalifying installation contractors, reviewing all bids, and executing the contracts. The installation will consist of the following phases: recovery wells, piping, treatment equipment, and start up.
The consultant will also be responsible for system-performance monitoring, which consists of sampling the groundwater, monitoring wells on a quarterly basis, and sampling the groundwater treatment-system discharge.
Prepare a work breakdown structure (WBS) for this project with activities corresponding to a two-level task and subtask hierarchy. Number the WBS codes so that the level of each activity is clearly identified. Do not worry about indentation.
8. (TCO B) You are reaching the end of your graduate-school program, and you are planning a large party to celebrate your success! You have rented out the local forest preserve as the venue for your party. Applying your project-management skills, you want to ensure you have everything planned out, and you’ve asked your family and friends to be a part of your team to hold this party. At your party, you have made it clear to your team what you want to have delivered. After all, it’s your party–you can have whatever you want! Some of the key items you want at your party include
• graduation announcements;
• party invitations;
• live entertainment;
• games (for adults and for children);
• food;
• beverages; and
• convenience for all (parking, restroom facilities, etc.).
a) To ensure you have a clear scope for your team, create a 2-level WBS. Don’t forget to include your WBS numbering.
b) In your WBS, how many work packages have been created?
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Writedemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.