Estimating Project Times and Costs
Project Management Ch 5
6th Edition
Your Results:
The  answer for each question is indicated by a  .

 

1
The process of forecasting or approximating the time and cost of completing project deliverables is called
A)
Budgeting
B)
Predicting
C)
Estimating
D)
Planning
E)
Guesstimating

2
What is the relationship between organizational culture and estimating?
A)
There is no relationship
B)
Cultural norms affect the accuracy of estimates
C)
Culture determines whether estimates are made
D)
Estimating alters cultural norms
E)
Estimating and culture are independent

3
A good starting point for developing time and cost estimates is
A)
Past experience
B)
Work packages
C)
Task analysis
D)
Time and motion studies
E)
Work breakdown structure

4
Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
A)
Padding estimates
B)
Planning horizon
C)
Project structure
D)
People
E)
Organization culture

5
Which of the following is a good condition for top-down estimating?
A)
Cost and time important
B)
Fixed price contract
C)
Customer wants details
D)
Internal, small project
E)
Large scale project involving several sub-contractors

6
Which if the following does NOT help describe a bottom-up estimating approach?
A)
They are made by someone who uses experience and/or information from someone else to determine overall project cost and duration.
B)
They establish low-cost, efficient methods for completing activities
C)
They establish low-cost, efficient methods for completing activities
D)
Estimates are made at the work package level and then “rolled up” to determine estimates for major deliverables and for the project itself
E)
They can take place after the project has been planned in detail.

7
Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs, outputs, inquires, files, and interfaces. Which of the following methods is he using?
A)
Ratio
B)
Template
C)
Apportion
D)
Function point
E)
Learning curve

8
Laura is forecasting the time and cost of developing an intranet for a new customer. Her department has completed six such intranets for customers during the last two years. Although the proposed system is about the same size as the others she estimates that it will take about 10 percent less time and money. Which of the following methods is she using?
A)
Ratio
B)
Template
C)
Apportion
D)
Function point
E)
Learning curve

9
Which of the following describes the consensus method?
A)
Only should be used for projects that require the same task, group of tasks, or product be repeated several times
B)
Uses several people with relevant experience regarding the task at hand to make time and cost estimates
C)
Uses pooled experience of senior and/or middle managers to estimate the total project duration and cost.
D)
Uses the number of square feet to estimate the total cost and time of the project
E)
Uses weighted macro variables or major parameters such as the number of inputs or outputs to estimate the total cost and time of the project

10
Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach?
A)
Parametric procedures applied to specific tasks
B)
Template method
C)
Apportion method
D)
Range estimating
E)
Learning curve

11
The salary of the project manager would be an example of what type of cost found in a project?
A)
Labor
B)
Direct
C)
Direct project overhead
D)
General and administrative overhead
E)
Salary

12
Which of the following would best represent direct project costs?
A)
Only labor
B)
Only materials
C)
Only equipment
D)
Both labor and materials
E)
Labor, materials and equipment

13
Companies are using which of the following for improving the estimating process for future projects?
A)
Adjusting estimates based on individual forecasting abilities
B)
Benchmarking and using the experience of other companies
C)
Using time and motion studies
D)
Creating historical databases of previous projects
E)
Establishing an estimating training course for all employees

14
Reasons why estimating time and cost are important include all of the following EXCEPT
A)
To schedule work
B)
To determine how long the project should take and cost
C)
To develop cash flow needs
D)
To determine how well the project is progressing
E)
To help establish a project selection process

15
Refining estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of:
A)
Hidden interaction costs
B)
Things going wrong on a project
C)
Normal conditions not applying
D)
Changes in project scope
E)
There is never a good reason to refine estimates
 

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order