Project Management Ch 9 – 6th Edition Reducing Project Duration

Project Management Ch 9 – 6th Edition Reducing Project Duration

Reducing Project Duration
Project Management Ch 9
6th Edition

Your Results:
The  answer for each question is indicated by a  .

 

1
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by:
A)
Imposed project deadlines
B)
Time to market
C)
Unforeseen project delays
D)
High overhead
E)
Incentive contracts

2
Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by:
A)
Imposed project deadlines
B)
Time to market
C)
Unforeseen project delays
D)
High overhead
E)
Incentive contracts

3
In a Project Cost-Duration Graph, total project costs are a sum of
A)
Labor, material and equipment costs
B)
Direct costs plus interest
C)
Direct labor costs and the project manager’s salary
D)
Direct costs and the project manager’s salary
E)
Direct and indirect costs

4
Which of the following is NOT considered a project indirect cost?
A)
Supervision
B)
Consultants
C)
Equipment
D)
Interest
E)
The project manager’s salary

5
Before crashing, direct costs for an activity represent normal costs, which typically mean low cost, efficient methods for completing the activity in a(n) ________ amount of time.
A)
Normal
B)
Budgeted
C)
Optimized
D)
Expected
E)
Targeted

6
As a project is crashed and project duration is reduced, direct costs typically
A)
Increase
B)
Become unstable
C)
Decrease
D)
Become unreliable
E)
Stay the same

7
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
A)
Normal
B)
Reserve
C)
Crash
D)
Accelerated
E)
Expedited

8
Cost slope can be determined by dividing the
A)
Run by the rise
B)
Rise by the run
C)
Crash cost by the normal cost
D)
Normal cost by the crash cost
E)
Indirect cost by direct cost

9
In selecting the best activity to crash you would first select the activity with the
A)
Earliest start time
B)
Most steep slope
C)
Least steep slope
D)
Longest duration
E)
Largest crash time

10
Reducing project duration
A)
Involves crashing all activities to their crash point
B)
Can only be done when resources are not constrained
C)
Is always more expensive
D)
Tends to increase network sensitivity
E)
Should be considered for all projects

11
The relationship between the normal point and the crash point is assumed to be:
A)
Linear
B)
Curvilinear
C)
Variable
D)
Conversely related
E)
Exponentially related

12
When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of
A)
Fast-Tracking
B)
Using critical-chain project management
C)
Reducing project scope
D)
Compromising quality
E)
Doing it twice- first fast and then ly

13
One way of reducing project costs is identifying tasks that _________ can do themselves.
A)
Vendors
B)
Suppliers
C)
Customers
D)
Company employees
E)
Project teams

14
Which of the following projects would be least beneficial if additional resources were added?
A)
Splitting and stacking a cord of wood
B)
Developing new software
C)
Harvesting a crop by hand
D)
Building a cabin
E)
Moving to a new house

15
It is going to cost $80,000 a day to simply house and feed a construction crew in the farthest reaches of Northern Alaska. This is an example of reducing project duration due to
A)
Imposed project deadlines
B)
Time to market
C)
Unforeseen project delays
D)
High overhead
E)
Incentive contracts

 

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order