Activity Immediate Predecessors Activity Time
A 5 days
B A 9 days
C A 8 days
D B 6 days
E B, C 4 days
F E 4 days
G D, F 3 days

The minimum time required to complete the project is:

A)23 days

B)24 days

C)25 days

D)39 days

E) none of the above

2. Use the network given in the Word file in the Final Examination Session under Course Content. The early start time (ES) for job G is:

A) 13

B) 16

C) 21

D) 25

E) 38

3. Use the network given in the Word file in the Final Examination Session under Course Content. The late finish time (LF) for job C is

A) 7

B) 14

C) 16

D)21

E) 22

4. Use the network given in the Word file in the Final Examination Session under Course Content. The critical path is given by:

A) A ? B ? E ? H

B) A ? B ? F ? H

C) A ? B ? F ? G ? H

D) A ? C ? F ? H

E) A ? C ? F ? G ? H

5. Use the network given in the Word file in the Final Examination Session under Course Content.

The minimum time required to complete the project is:

A)23 days

B)25 days

C)29 days

D)31 days

E) none of the above

6. Use the network given in the Word file in the Final Examination Session under Course Content. The slack at activity D is:

A) 0

B) 5

C) 8

D) 13

E) None of the above

7. One part of a PERT project, installing equipment, will most likely be completed in 6 days. However, if there are no worker absences, the equipment can be installed in 3 days. If a members the work force happens to catch Bubonic Flu, this year’s disease, the installation will take 15 days. What is the expected time (te) for the equipment installation?

A) 3 days

B) 6 days

C) 7 days

D) 8 days

E) 15 days

8. A firm desires to control inventory levels so as to minimize the sum of holding and order costs. It costs the firm $50 to place an order. The firm estimates its inventory carrying costs at $2/unit/year. Weekly demand is 100 units, and there are 50 weeks in the work year. The item costs $10 per unit. The lead-time for the product is 3 weeks. Assume that there are 5 working days per week.

What quantity of items should the firm order each time so as to minimize total inventory costs, i.e., what is the EOQ?

A) 100

B) 224

C) 500

D) 1000

E) none of the above

9. Using the data of Question 8: If 400 units are ordered each time (i.e., EOQ = 400), then what will be thetotal annual holding cost?

A) $100

B) $200

C) $400

D) $800

E) $4000

10. Using the data of Question 8: If 200 units are ordered each time,how many orders will be placed in a year?

A) 2

B) 5

C) 10

D) 20

E) 25

11. Using the data of Question 8: If 200 units are ordered each time, then thetime between orders (in working days) is

A) 2

B) 5

C) 10

D) 20

E) 25

12. Using the data of Question 8: If 1000 are ordered each time, then what will be thetotal annual order cost?

A) $50

B) $100

C) $200

D) $250

E) $300

13. Use the data of Question 8 and assume no safety stock or service level requirement. In order not to run out of stock before the receipt of a new order, at what inventory level should the firm place an order? That is, what is the reorder point equal to?

A) 50

B) 160

C) 200

D) 300

E) 400

14. Given that unit cost = $25, annual carrying charge = 10%, annual demand = 7500 units and ordering cost = $15 per order.Assume that there are 50 weeks in the work year and 5 working days per week. The lead-time for the product is2weeks. The EOQ is:
A) 150 units
B) 212.13 units
C) 300 units
D) 500 units
E)none of the above

15. Lincoln Machine Tool Company maintains an inventory pool consisting of 10 items. Each of these items has a unique demand pattern and may require a different kind of inventory management system. The annual demand pattern and the unit cost of these items are given in the following table. Classify the items in A, B, and C categories according to annual dollar usage.

Annual Usage Unit Cost
Item Type in thousands in Dollars
Item 1 10 $2.50
Item 2 30 $1.25
Item 3 20 $16.00
Item 4 10 $0.75
Item 5 20 $3.00
Item 6 33 $2.50
Item 7 60 $14.25
Item 8 22 $10.00
Item 9 100 $2.75
Item 10 500 $4.25

Using the above data,Item 7 will be classified as:

A) A item

B) B item

C) C item

D) None of the above

16. Using the data of Question 15,Item 6 will be classified as:

A) A item

B) B item

C) C item

D) None of the above

17. Using the data of Question 15,Item 8 will be classified as:

A) A item

B) B item

C) C item

D) None of the above

18. One end itemA requires three component parts:B,C, andD. The bill of material indicates that for each completedA, 3 units ofB, 2 units ofC, and 1 unit ofD are required. Current inventory for the four items is as follows: There are 18As, 40Bs, 50Cs and 35Ds in stock. If the lead time for all items is one week and there are no scheduled receipts for any item, how many units of productA can be delivered to customers at the start of next week (week 2)?

A) 35
B) 31
C)25
D) 13
E) None of the above

Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks.

Item D 1 2 3 4 5 6
Gross Requirements 100 300 100 300 200 50
On Hand/ Scheduled Receipts 700 600 300 200 0 0
Net Requirements 0 0 0 ? 200 50
Planned Order Releases 100 ? 50

19. The value of entryA is:

A) 100

B) 200

C) 300

D) 700

E) None of the above.

20. The value of entryB is:

A) 50

B) 200

C) 250

D) 300

E) None of the above

21. Use the BOM given in the Word file in the Final Examination Session under Course Content. If the master schedule calls for the production of 50 units ofA, how many units ofE are needed?

A) 50

B) 100

C) 200

D) 400

E) None of the above

22. Use the BOM given in the Word file in the Final Examination Session under Course Content. If the MPS calls for the production of 50 units of itemA, how many units of itemD are needed?

A) 100

B) 150

C) 300

D) 400

E) None of the above

23. Use the BOM given in the Word file in the Final Examination Session under Course Content Now assume that 50 units of itemAare called for by the MPS. On-hand inventory consists of 20 units each of itemsA,B, D andE. What is the net requirement for itemD?

A) 40

B) 100

C) 120

D) 140

E) 160

24. The master production schedule for two products, A and B, is shown below. To manufacture item A, four (4) units of component C are required. To manufacture item B, three (3) units of component C are required. Using this information, determine the gross requirements for component C to start week 1.

Master Production Schedule: Wk 1
Product A 30
Product B 25

A) 195

B) 220

C) 155

D) 190

E) None of the above

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order