Question Question 1 of 20 5.0 Points Allocating specific, limited resources to specific activities is called:

Question Question 1 of 20 5.0 Points Allocating specific, limited resources to specific activities is called:

Question

Question 1 of 20 5.0 Points
Allocating specific, limited resources to specific activities is called:

A. resource allocation.

B. resource leveling.

C. resource tracking.

D. expediting a project.
Reset Selection

Mark for Review What’s This?

Question 2 of 20 5.0 Points
The primary cause of concern in resource allocation is:

A. labor cost.

B. resource scarcity.

C. lack of solution methodologies.

D. parallel activities.
Reset Selection

Mark for Review What’s This?

Question 3 of 20 5.0 Points
A project that cannot go over budget is considered:

A. time constrained.

B. schedule constrained.

C. resource constrained.

D. performance constrained.
Reset Selection

Mark for Review What’s This?

Question 4 of 20 5.0 Points
The task duration with standard-practice resource usage is referred to as the:

A. expected task duration.

B. nominal task duration.

C. crash duration.

D. normal task duration.
Reset Selection

Mark for Review What’s This?

Question 5 of 20 5.0 Points
A task has a normal duration of 9 days and crash duration of 7 days. Its normal cost is $40 and its crash cost is $100. What is the crash cost per day?

A. $140

B. $70

C. $50

D. $30
Reset Selection

Mark for Review What’s This?

Question 6 of 20 5.0 Points
What is an expediting technique in which the design and planning phases of a project are not actually completed before the building phase is started?

A. resource loading

B. fast-tacking

C. crashing

D. critical path
Reset Selection

Mark for Review What’s This?

Question 7 of 20 5.0 Points
Resource __________ refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.

A. expediting

B. leveling

C. loading

D. allocation
Reset Selection

Mark for Review What’s This?

Question 8 of 20 5.0 Points
Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project’s duration?

A. As soon as possible

B. As late as possible

C. Shortest task duration first

D. Minimum slack first
Reset Selection

Mark for Review What’s This?

Question 9 of 20 5.0 Points
Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?

A. As soon as possible

B. As late as possible

C. Shortest task duration first

D. Minimum slack first
Reset Selection

Mark for Review What’s This?

Question 10 of 20 5.0 Points
Several projects can be linked together with:

A. virtual activities.

B. nominal activities.

C. pseudoactivities.

D. ER links.
Reset Selection

Mark for Review What’s This?

Question 11 of 20 5.0 Points
Which of the following is NOT commonly used to help select a priority rule?

A. Schedule slippage

B. Resource utilization

C. In-process inventory

D. Cost overruns
Reset Selection

Mark for Review What’s This?

Question 12 of 20 5.0 Points
Which of the following is a measure of the amount by which a project is delayed by application of a leveling rule?

A. Schedule inflation

B. Schedule progression

C. Schedule efficacy

D. Schedule slippage
Reset Selection

Mark for Review What’s This?

Question 13 of 20 5.0 Points
According to research, the best overall priority rule is:

A. as soon as possible.

B. as late as possible.

C. shortest task duration first.

D. minimum slack first.
Reset Selection

Mark for Review What’s This?

Question 14 of 20 5.0 Points
The practice of assigning project team members to multiple projects is called:

A. concurrent engineering.

B. parallel activities.

C. fast-tracking.

D. multitasking.
Reset Selection

Mark for Review What’s This?

Question 15 of 20 5.0 Points
The safety time added to chains other than the critical chain is called the:

A. feeding buffer.

B. project buffer.

C. path buffer.

D. critical buffer.
Reset Selection

Mark for Review What’s This?

Question 16 of 20 5.0 Points
In traditional Critical Path Method, a second estimate, referred to as the __________ duration, is made based on the resources required to expedite the task.

A. normal task

B. assumed

C. crash

D. approximated
Reset Selection

Mark for Review What’s This?

Question 17 of 20 5.0 Points
When task durations are estimated, an assumption is made that task resources are set at __________ levels.

A. standard

B. normal

C. manageable

D. low
Reset Selection

Mark for Review What’s This?

Question 18 of 20 5.0 Points
Used primarily in the construction industry, the term __________ refers to a technique in which the design and planning phases of a project are not actually completed before the building phase is started.

A. “fast-tracked”

B. “expediting”

C. “crash”

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order