Questionroject ManagementShale Oil CompanyShale Oil Company’s Aston, Ohio, manufacturing complex comprises seve

Questionroject ManagementShale Oil CompanyShale Oil Company’s Aston, Ohio, manufacturing complex comprises seve

Question

roject Management
Shale Oil Company
Shale Oil Company’s Aston, Ohio, manufacturing complex comprises several operating units. These units process the crude oil that is pumped through and transform it into a multitude of hydrocarbon products. The units run 24 hours a day, 7 days a week, and must be shut down for maintenance on a predetermined schedule. One such unit is Distillation Unit No. 5, or DU5. Studies have shown that DU5 can operate only 3 years without major equipment breakdowns, and excessive loss of efficiency. Therefore, DU5 is shut down every 3 years for cleaning, inspection, and repairs.

DU5 is the only distillation unit for crude oil in the Aston complex, and its shutdown severely affects all other operating units. Some of the production can be compensated for by Shale refineries in other locations, but the rest must be processed and stored before the shutdown. Without proper planning, a nationwide shortage of Shale gasoline could occur. The time of DU5’s shutdown is critical, and the length of time the unit is down must be kept to a minimum to limit production loss. Shale uses PERT as a planning and controlling tool to minimize shutdown time.

The first phase of a shutdown is to open and clean the equipment. Inspectors can then enter the unit and examine the damage. Once damages are determined, the needed repairs can be carried out. Repair times can vary considerably, depending on what damage the inspection reveals. Based on previous inspection records, some repair work is known ahead of time. Thorough cleaning of the equipment is also known to improve the unit’s operating efficiency. The table below lists the many maintenance activities and their estimated completion times.

DISCUSSION QUESTIONS

1. Determine the expected shutdown time and the probability that the shutdown can be completed 1 week earlier.

2. What are the probabilities that Shale finishes the maintenance project 1, 2, 3, 4, 5, or 6 days earlier?

3.Shale Oil is considering increasing the budget to shorten the shutdown. How do you suggest the company proceed?

Preventive Maintenance of DU5
Activities Time Estimates (in Days)
Optimistic Most Likely Pessimistic
1-2 Circulate wash water throughout unit 1 2 2.5
2-3 Install blinds 1.5 2 2.5
3-4 Open and clean vessels and columns 2 3 4
3-5 Open and clean heat exchangers; remove tube bundles 1 2 3
3-6 Open and clean furnaces 1 2 4
3-7 Open and clean mechanical equipment 2 2.5 3
3-8 Inspect instrumentation 2 4 5
4-9 Inspect vessels and columns 1 2 3
5-10 Inspect heat-exchanger shells 1 1.5 2
5-11 Inspect tube bundles 1 1.5 2
6-12 Inspect furnaces 2 2.5 3
6-17 Retube furnaces 15 20 30
7-13 Inspect mechanical equipment 1 1.5 2
7-18 Install new pump mechanical seals 3 5 8
8-19 Repair instrumentation 3 8 15
9-14 Repair vessels and columns 14 21 28
10-16 Repair heat-exchanger shells 1 5 10
11-15 Repair tube bundles; retube 2 5 10
12-17 Repair furnaces 5 10 20
13-18 Repair mechanical equipment 10 15 25
14-20 Test and close vessels and columns 4 5 8
15-16 Install tube bundles into heat-exchanger shells 1 2 3
16-20 Test and close heat exchangers 1 2 2.5
17-20 Test and close furnaces 1 2 3
18-20 Test and close mechanical equipment 1 2 3
19-20 Test instrumentation 2 4 6
20-21 Pull blinds 1.5 2 2.5
21-22 Purge all equipment with steam 1 3 5
22-23 Start up unit 3 5 10

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order