Chat with us, powered by LiveChat WHICH CRITICAL PATH ACTIVITY WOULD BE THE MOST LOGICAL CHOICE FOR THE FIRST ACTIVITY TO CRASH? | Writedemy

WHICH CRITICAL PATH ACTIVITY WOULD BE THE MOST LOGICAL CHOICE FOR THE FIRST ACTIVITY TO CRASH?

WHICH CRITICAL PATH ACTIVITY WOULD BE THE MOST LOGICAL CHOICE FOR THE FIRST ACTIVITY TO CRASH?

1. Using the information in PERT Network Diagram 1 and Table 1, calculate the expected activity time (t) in weeks for each activity

2. Using the information in PERT Network Diagram 1 and Table 1, calculate the variance for the estimated activity time for each activity.

3. Using the information in PERT Network Diagram 1 and Table 1, calculate the overall estimated activity time in weeks for each path through the network and identify which path constitutes the critical path.

4. Using the information in PERT Network Diagram 1 and Table 1, calculate the standard deviation for the project.

5. Using the information in PERT Network Diagram 1 and Table 1, calculate the probability of the project critical path activities being completed in less than or equal to 18 weeks.

6. Using the information in PERT Network Diagram 1 and Table 1, calculate the Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity.

7. Using the information in PERT Network Diagram 1 and Table 1, calculate the slack time in weeks for each activity.

8. Using the information in PERT Network Diagram 1 and Table 1, calculate the total budgeted costs for weekseven of the project based upon using the Earliest Start Date for each activity.

9. Using the information in PERT Network Diagram 1 and Table 1, calculate the total budgeted costs for week eleven of the project based upon using the Latest Start Date for each activity.

10. Using the information in PERT Network Diagram 1 and Table 1, calculate the difference between the total budgeted costs for week seventeen of the project based upon using the EarliestStart Date for each activity and week seventeen of the project based upon using the Latest Start Date for each activity.

11. Using the information in PERT Network Diagram 1 and Table 1, calculate the value of work completed and activity difference for each activity. Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost underrun) at this particular point in the project?

12. Using the information in PERT Network Diagram 1 and Table 1, calculate the overall cost overrun or cost underrun for the project at this particular point in the project.

13. Using the information in PERT Network Diagram 1 and Table 1, crash the network in order to reduce the estimated project duration to 18 weeks while minimizing the overall crash cost.

a. Which critical path activity would be the most logical choice for the first activity to crash?

b. Which critical pathactivity would be the most logical choice for the second activity to crash?

c. What is the total estimated cost associated with crashing the network to reduce the estimated project duration to 18 weeks at the lowest possible overall crash cost?

d. After successfully crashing the network to reduce the estimated project duration to 18weeks, which path(s) through the crashed network constitutes the critical path(s)?

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Writedemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order